May 2017 Project Update


·       The site grading project is well underway. Favorable weather has assisted in significant progress.

·        Surcharge project is complete. Ongoing testing continues; positive results are anticipated.

·        The 59th street reroute project is underway.

·        City of Williston continues to collaborate on establishing a GMP (Guaranteed Maximum Price) for the new terminal at XWA Williston Basin International Airport.

·        In early May, the State of North Dakota allocated approximately $35,000,000 in grants to the XWA Williston Basin International Airport project.  


Keep up to date by checking out the exciting photos and videos posted from onsite work...






 

 