March Updates
March 29, 2017



The RFQ for the Tribal Coordination Scope of Services was awarded March 17, 2017 to Ulteig Engineering. They were selected through the quality based selection process.   Their services will be utilized for all earth disturbing related activities and mainly focused on the 2017 construction season. Aaron Lauinger is the point of contact for Ulteig Engineering. He may be reached at Aaron.Lauinger@Ulteig.com or via phone at (218) 234-9905.

The RFQ for the Airport Terminal Project was awarded on March 28, 2017 to JE Dunn. They will be responsible for the construction of the $40 million, 115,000-sq. ft. terminal building that will be two stories and feature an escalator, full-service restaurant, gift shop, and several comfortable lounges to wait for arriving passengers. Marc Mellmer, Operations Manager, is the point of contact for JE Dunn. He may be reached at marc.mellmer@jedunn or by phone at (612)-282-9517.

Regarding the ND State participation on this project, State share is presently projected at 24% which equates to $57-$58 million dollars.  The state is currently in legislative session and there should be more information in the next few weeks. 

In the DOING BUSINESS section: 

If you are looking for information on upcoming bid requests related to the XWA Airport, please select the Doing Business tab located on the top navigation of this site.  You may also contact Rick Skumavc at rick@cardonglobal.com or via phone at 701-500-6873 for any questions.   

Upcoming 2017 bids to be looking for in the Doing Business section include:

Waste Water Collection
Water Service
Airport Access Road
Primary Runway
NAVAIDS
Communications
Electrical Vault
Commercial Parking Lot



 

 